LIFT STATION BHI / ExxonMobil 2015

skids
MANUFACTURING SKIDS BHI 2015
January 17, 2017
UN TOWER
CONSTRUCTION AND INSTALLATION OF COMMUNICATIONS TOWER AT UNAMI 2016-2017
March 22, 2017
lift station

Client: BHI / ExxonMobil
Date: April 2015
Location: Iraq
LIFT STATION BHI / ExxonMobil 2015

This job is for the extension of the Water Lift Station. Exxon Mobile needed more water injection for the oil wells, so the plan is to add two more units of pump sets to the old Lift Station. The following are the procedures in Lift Station;

  • Prepare the Land

  • Add Sub-Base Compact

  • Cast Concrete Pad of the New Pumps

  • In addition of disassemble the Sun Shade to Make Room for the Installing of Pumps

  • Adding T- Walls and make the Main Gate Wider.